December Bulletin . Click here...
November Bulletin Click here...
October Bulletin Click here...
September Bulletin Click here...
August Bulletin Click here...
July - Second CPMCL AGM held.
July Bulletin Click here...
June Bulletin Click here...
May - Amended times for fountains and lights Click here...
May Bulletin Click here...
April Bulletin Click here...
March Bulletin Click here...
February - Our electrical contractor is going to replace the Leg 2 light driver with several smaller drivers so that in future if the lights fail, only a small section of the path lights will be out.
February - Debris blown in to the feature by Storm Imogen affected the fountains on Leg 2 causing overspray.
February Bulletin Click Here...
January Bulletin Click here...
December Bulletin - Click here...
November Bulletin - Click here...
October Bulletin - Click here...
September Bulletin - Click here...
Interim Bulletin - Click here...
August Bulletin - Click here...
July 2017 - Excavation of water feature path - Ongoing tests have identified possible damage to pipework buried in the San Juan Court side of the pathway. Parts of the path will be closed while contractors begin excavating to reach the pipework, carry out a camera survey and do the repairs.
July Bulletin - Click here...
June Bulletin - Click here...
May Bulletin - Click here...
April Bulletin - Click here...
March Bulletin - Click here...
February Bulletin - Click here...
January Bulletin - Click here...